Indio Activated Sludge Plant / Sludge Dewatering Facilities

W. M. Lyles Co.
Indio, California

Indio Activated Sludge Plant / Sludge
Dewatering Facilities

Contract Amount: $24,401,821.00
Completion Date: May, 2009

Modifications to the existing activated sludge treatment system; replacement of the existing chlorination and dechlorination systems; addition of a new sludge dewatering building with two new belt presses; addition of a new effluent outfall system, and related earthwork, pumping, piping, electrical, and control systems. The work also includes three new aeration blowers, three new 95 foot diameter secondary clarifiers, and a new hypochlorite storage building. The existing activated sludge plant has a permitted capacity of 5 million gallons per day (mgd) and, after construction is complete, the activated sludge plant capacity will be increased to approximately 7.56 mgd.

Owner:
Valley Sanitary District
45500 Van Buren
Indio, CA 92201

Owner Contact:
Mike Laponic
760-347-2356

W. M. Lyles Co. PM:
Dave Dawson

Design Engineer:
Lee & Ro, Inc.
1199 South Fullerton Road
City of Industry, CA 91748

Engineer Contact:
Kirk Saiki
626-912-3391

WML_Indio_2 WML_Indio_3