Contract Amount: $81,814,908
Completion Date: March, 2010

Construction of a 12 MGD Industrial Wastewater Treatment Facility including, but not limited to: Dissolved Air Floatation (DAF) units, aeration lagoons for aerobic treatment with the associated civil, mechanical, structural, electrical and instrumentation work; new rectangular concrete tanks to be used as Sequencing Batch Reactors (SBR); Dentrification filters; blower building complete with associated civil, mechanical, structural, electrical and instrumentation work; circular concrete anaerobic sludge digesters with circulation and heating systems; standby generators; earthwork, grading, and drainage systems; roadways, and yard piping. The project is an expansion and upgrading of an existing industrial wastewater treatment plant. The existing plant is to remain fully operational during construction and producing effluent of the quality as being produced before construction of this project commences.

Cal/OSHA Golden Gate Partnership Award Recipient; 160,000 man-hours with no lost-time incidents

Owner:
City of Tulare
1875 S. West Street
Tulare, CA 93274

Owner Contact:
Richard Bono
(559) 685-2360

W.M. Lyles Co. PM:
Ken Strosnider

Lyles Mechanical Co. PM:
Matt Teixeira

Design Engineer:
Parsons
100 W. Walnut Street
Pasadena, CA 91124

Engineer Contact:
Masoud Samee
(909) 274-3786

WML_TulareIWWTP_2